Red Line Train Derailment Caused by Faulty Axle: Officials

MBTA and MassDOT officials are expected at a joint board meeting Monday, which may include the discussion of what caused the June 11 Red Line train derailment

Find NBC Boston in your area

Channel 10 on most providers

Channel 15, 60 and 8 Over the Air

    processing...

    NEWSLETTERS

    MBTA Says Broken Axle Caused Red Line Derailment

    Following an extensive investigation, MBTA officials now say a broken axle is to blame for a derailment on the Red Line back in June.

    (Published Monday, Sept. 16, 2019)

    MBTA officials said Monday that a June derailment on the Red Line was caused by a fractured axle, three months after the incident caused major delays.  

    Officials said poor electrical connectivity between a ground brush and ground ring caused stray electrical arcing on the surface of the axle. Over time, this weakened the axle and led to the failure. 

    The revalation was the result of a "comprehensive assessment" of the incident that included analysis conducted by an independent engineering firm, officials said.  

    Officials from the MBTA’s Fiscal and Management Control Board met with MassDOT’s Board of Directors for a joint session Monday, in which officials discussed the results of the assessment.

    Meeting Could Reveal Cause of Red Line Derailment

    [NECN] Meeting Could Reveal Cause of Red Line Derailment

    After more than three months, we could finally learn what caused an MBTA Red Line train to derail in June.

    (Published Monday, Sept. 16, 2019)

    MBTA Dep. General Manager Jeff Gonneville said going forward, it was on the MBTA to make sure technicians know the right procedures.

    "That is on us. That is on the MBTA to ensure we are giving our technicians the right procedures they should be following," Gonneville said. "In full transparency, we, the authority, has to ensure that our technicians are doing a more precise inspection of the ground ring.

    The MBTA has completed an "ultrasonic" inspection of all Red Line vehicle axles in an attempt to identify any other fractures or other potential issues, officials said. 

    Orange, Blue and Green Line vehicles are also being inspected, as are ground rings on MBTA trains.  

    The Red Line train derailed June 11, hitting bungalows that housed signal systems and causing significant damage. 

    The incident, prompted severe delays and frustration among passengers.

    New Video Captures Red Line Derailment

    [NECN] New Video Captures Red Line Derailment

    Footage from the MBTA shows sparks flying out of a Red Line train as it goes off the tracks.

    (Published Friday, July 19, 2019)

    Transit officials said crews will likely be done repairing the signals by October.

    Jimmy O'Brien, President of the Boston Carmen's Union, released a statement Monday in response to the Red Line derailment.

    "The MBTA claims a commitment to investing in the system while simultaneously boasting about cost savings in the operating budget. Cuts to the operating budget and the elimination of jobs resulted in cuts to inspections and testing – including the ultrasonic testing that could have detected the problem that resulted in the Red Line derailment. There are no corners to be cut when it comes to ensuring safety and service for our riders. A real investment in the MBTA means investing in the personnel and services required to ensure safety and satisfaction for passengers," O'Brien said.


    Get the latest from NBC Boston anywhere, anytime:

    App

    Download our FREE app for iPhone, iPad and Android. You can also follow us on Facebook, Twitter and Instagram, and sign up for our e-mail newsletters.